Expansion plans for Whitehaven Coal's Narrabri Underground Mine have been given conditional approval by the Independent Planning Commission (IPC).
Subscribe now for unlimited access.
$0/
(min cost $0)
or signup to continue reading
The company sought permission to extend longwall operations to the south of its existing mine, located between Gunnedah and Narrabri, and extract an additional 82 million tonnes of coal to 2044.
The Department of Planning and Environment completed its whole-of-government assessment of the Narrabri Underground Mine Stage 3 Extension Project in January this year; however, the state significant development application came to the Commission for determination under Ministerial delegation.
A three-member Commission panel granted development consent for the project subject to 152 conditions.
"The Commission finds that, on balance, the Application is not inconsistent with [ecologically sustainable development] principles, and that the Project would achieve an appropriate balance between relevant environmental, economic and social considerations," the Statement of Reasons for Decision reads.
Previously:
In making its determination the Commission took into account the NSW Government's policies on mining and emissions reductions and also acknowledged concerns - particularly about greenhouse gas emissions, including the increased methane that is predicted to be released beyond 2030.
The Commission has set strict performance measures to curb the intensity of the mine's Scope 1 and Scope 2 greenhouse gas emissions, which Whitehaven must comply with during the life of the mine.
Whitehaven will also be required to complete an Emissions Minimisation Plan.
"Subject to the imposed conditions, the Commission is satisfied that the Project can achieve the requirements of the Resources SEPP [State Environmental Planning Policy (Resources and Energy) 2021] and the relevant strategic policy positions with respect to the reduction of fugitive emissions and the recognition of the importance of the continuation of the extraction and exportation of coal to the NSW economy," the decision read.
The Commission has also put in place measures to ensure local groundwater users affected by the mine's expansion receive adequate compensation.
"The Commission is of the view that should any groundwater users be affected by the Project, the proposed make good provisions and contingency measures would then apply... [and] would be sufficient in adequately compensating affected groundwater users," it noted.
"[T]he Applicant must provide a compensatory water supply to any landowner of privately-owned land whose rightful water supply is adversely and directly affected... [and] must also provide and alternative long-term supply of water that is equivalent, in quality and volume, to the loss attributable to the development."
Air quality, noise impacts, subsidence, traffic, visual impacts and heritage, particularly Aboriginal cultural heritage were among the other issues considered by the Commission, which concluded these impacts could be effectively avoided, minimised or offset through its imposed conditions of consent.
The Commission also found there was considerable local support for the project, which it found would generate "net positive economic benefits" through local employment, royalties and tax revenue.
Our journalists work hard to provide local, up-to-date news to the community. This is how you can continue to access our trusted content:
- Bookmark northerndailyleader.com.au
- Make sure you are signed up for our breaking and regular headlines newsletters
- Follow us on Twitter
- Follow us on Instagram
- Follow us on Google News