PLANNING costs and bureaucracy are two reasons the proposed Dungowan Dam project's budget could increase according to the Deputy Prime Minister Barnaby Joyce.
Subscribe now for unlimited access.
$0/
(min cost $0)
or signup to continue reading
Originally slated to cost $480 million when first announced in October 2019, an assessment released to Parliament by the Productivity Commission in February suggested the project could blow past its budget and was "likely unviable".
However, Mr Joyce said the proposed blowout was "just an assessment" and put the alleged inflated costs down to delays in planning.
"What we have to look at when we talk about cost is how much of that cost is going to studies?," Mr Joyce said.
"I would like to see more equipment at work rather than a whole myriad of bureaucracy at work because these costs are not up at the site, but are costs down in Sydney.
"The cost is obviously not in the construction, it's in the bureaucracy, so the problem is not in the project but in the process tied to it.
"I'll tell you right now, the cost is sitting in Sydney with bureaucracy and that is where we have got to concentrate."
The project has sparked criticism from several sectors for beginning early works before the business case has been released, which is expected to be handed down later this year.
The Productivity Commission, as part of its National Water Reform, was one of the most damning reviews as it found the development was likely to blow its estimated $480 million budget so significantly it would likely be unviable.
However, federal Water Minister Keith Pitt, who was alongside Mr Joyce in Tamworth on Monday, took aim at the commission and said he was confident the project would deliver greater water security to local producers.
"I'll be brutally frank, the Productivity Commission is a bunch of economists who don't have to do the work and they don't have to worry about whether they get their irrigation allocation next year, or pay their bank or workers, or meet all the financial requirements of doing business in this country," Mr Pitt said.
"We are committed to building dams and this is just one of many across the country.
Read also:
"I know there has been some delay in terms of the business case... but we want to make sure we get this right and we will work closely with the state government to make sure that happens."
Mr Joyce echoed Mr Pitt's sentiments saying he was not concerned the project would be built because "I am going to make sure they do build it."
The Leader contacted NSW Water Minister Melinda Pavey for comment but she did not respond before this article went to press.
Our journalists work hard to provide local, up-to-date news to the community. This is how you can continue to access our trusted content:
- Bookmark northerndailyleader.com.au
- Make sure you are signed up for our breaking and regular headlines newsletters
- Follow us on Twitter
- Follow us on Instagram
- Follow us on Google News